Job No: TR-2026-0050 PASS

SF 07 • Smoke Exhaust Fan

Hydrotek Engineering Co.

Hydrotek Engineering Co.

Technical Services Division

Technical Services Division
EQUIPMENT OVERHAUL & TEST REPORT
Job No: TR-2026-0050
Date: 13/05/2026
Overall Result: PASS
1. Equipment Details
Project Details Mushrif pumping station rehabilitation work
Tag / Equipment ID SF 07 Location LL
Equipment Name Smoke Exhaust Fan
Motor Specs 11 kW | 415 V | 18.0 A
2. Electrical & Insulation Checks
Test Parameter Measured Value Result
Motor Rewinding & Stator Check REPLACED AND TESTED OK PASS
Winding Resistance (Ohms) U–V: 0.848 Ω | V–W: 0.832 Ω | W–U: 0.840 Ω PASS
Insulation Resistance (500V DC) – Phase to Ground 442.88 MΩ (Min: > 5 MΩ) PASS
Insulation Resistance (500V DC) – Phase to Phase 477.15 MΩ (Min: > 5 MΩ) PASS
3. Mechanical Seal & Bearing Replacement
Component Checked Replacement Details / Part No. Result
Bearings – Drive End (DE) Part No: 6208 2Z/C3 • Brand: SKF (Explorer Series) (Replaced New) PASS
Bearings – Non-Drive End (NDE) Part No: 6206 2Z/C3 • Brand: SKF (Explorer Series) (Replaced New) PASS
Mechanical Seal & Leak Test N/A (Fan Motor Drive) • Static Leak Test: N/A PASS
4. Operational Run Test
Test Parameter Measured Value Result
Running Current (A) L1: 6.30 A | L2: 6.43 A | L3: 6.17 A PASS
Bearing Temperature (°C) DE: 44.5 °C | NDE: 43.2 °C (Normal) PASS
Vibration Level DE: 2.00 mm/s | NDE: 2.10 mm/s (Smooth) PASS
Rotation & Seal Check Rotation: Correct (CW) | Seal Leakage: Nil / None PASS
5. Sign-Off & Approvals
PREPARED BY:
ENG. JITHU THOMAS
Signature Date: 13/05/2026
INSPECTED BY:
ASWATH KUMAR HOSDURG
Signature Date: 13/05/2026
APPROVED BY:
ABU GEROGE
Signature Date: 13/05/2026
Hydrotek Engineering Co. • Equipment Overhaul & Test Certificate
REF: TR-2026-0050 • PAGE 1 OF 1