Kabd Water Treatment Plant - Pump & Motor Repair overhauling
Client: M/s. Contractor Co.
Facility / Site: Kabd Water Treatment Plant
Overhauling
Equipment & Pump Overhaul Schedule
Total of 4 pumps registered for this project
| Tag / ID | Pump Details & Type | Electrical Specs | Hydraulic Specs | Mechanical / Bearings | Status | Certificate & Actions |
|---|---|---|---|---|---|---|
|
PUMP
ABB Motor - 22kW
|
ABB Motor
End Suction Centrifugal Pump
Job: Completed complete overhaul including painting
|
22kW
415 V • 40.00 A
1450 RPM
|
Direct Fan/Motor |
DE: SKF
NDE: SKF
|
TESTED / PASS | |
|
MOTOR
WEG-22kW
|
WEG motor
TEFC Squirrel Cage Induction Motor
Job: Motor General Overhaul, Bearing Replacement & Testing
WEG •
|
22kW
415 V • 40.00 A
2900 RPM
|
Direct Fan/Motor |
DE: SKF
NDE: SKF
N/A (Electric Motor)
|
DELIVERED | |
|
PUMP
FHE 50-250/250
|
Horizontal Split-Case booster pump (Horizontal booster)
Horizontal booster
Job: REPLACEMENT OF BEARING AND OVERHAULING INCLUDING PAINTING
LOWARA • FHE 50-250/250
|
22 kW
415 V •
2900 RPM
|
Flow: 85 m³/hr
Head: 32 m
|
DE: 6309 2Z/C3
NDE: 6308 2Z/C3
Single Spring Elastomer Bellows Seal (Burgmann MG1)
|
TESTED / PASS | |
|
PUMP
FHE 50-250/250
|
Horizontal Split-Case booster pump
Horizontal booster
Job: Complete Pump Overhaul & Mechanical Seal Replacement
Lowara • FHE 50-250/250
|
22kW
415 V • 36.00 A
2900 RPM
|
Flow: 85 m³/hr
Head: 32
|
DE: 6311 2Z/C3
NDE: 6308 2Z/C3
Cartridge Balanced Mechanical Seal (EPDM)
|
TESTED / PASS |