Facility Maintenance • Kuwait

Mishref Pump Room Overhaul Schedule

Hydrotek Engineering Co. Technical Services Division • Real-time motor rewinding, mechanical overhaul tracking, and standardized test certification.

Total Equipment
60 Pumps & Motors
Completed
60 100% rate
Delivered
60 To Mishref Room
Certificates Ready
60 QC Signed
×

Equipment & Motor Repair Records 60

Showing page 2 of 4
Sr. Tag No • Location Equipment Details & Power Initial Status & Scope Progress / Remarks Test Certificate Actions
7
DPS 01 ML-1
Qty: 1 unit
Chemical dosing pump with motor (Scrubber)
0.25KW, 3PH, 415V
Condition: Motor and pump submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
25 Apr 2026
COMPLETED AND DELIVERED
7
DPS 02 ML-1
Qty: 1 unit
Chemical dosing pump with motor (Scrubber)
0.25KW, 3PH, 415V
Condition: Motor and pump submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
COMPLETED AND DELIVERED
7
DPS 03 ML-1
Qty: 1 unit
Chemical dosing pump with motor (Scrubber)
0.25KW, 3PH, 415V
Condition: Motor and pump submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
COMPLETED AND DELIVERED
7
DPS 04 ML-1
Qty: 1 unit
Chemical dosing pump with motor (Scrubber)
0.25KW, 3PH, 415V
Condition: Motor and pump submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
COMPLETED AND DELIVERED
8
SCR-1 LL
Qty: 1 unit
Emergency pump trench (Top motor)
1.5KW, 3PH, 415V
Condition: Motor submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
17 May 2026
COMPLETED AND DELIVERED
9
SCR-11 LL
Qty: 1 unit
Bar Screen -1 (Top motor)
0.55KW, 3PH, 415V
Condition: Motor submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
17 May 2026
COMPLETED AND DELIVERED
10
SCRV-11 LL
Qty: 1 unit
Bar Screen -1 (Bottom Motor)
2.98, 3PH, 415V
Condition: Motor submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
28 Apr 2026
COMPLETED AND DELIVERED
11
SCR-12 LL
Qty: 1 unit
Bar Screen -2 (Top motor)
0.55KW, 3PH, 415V
Condition: Motor submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
28 Apr 2026
COMPLETED AND DELIVERED
12
SCRV-12 LL
Qty: 1 unit
Bar Screen -2 (Bottom motor)
14.9KW, 3PH, 415V
Condition: Motor submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
03 May 2026
COMPLETED AND DELIVERED
13
SCR-21 LL
Qty: 1 unit
Bar Screen -3 (Top motor)
0.55KW, 3PH, 415V
Condition: Motor submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
02 May 2026
COMPLETED AND DELIVERED
14
SCRV-21 LL
Qty: 1 unit
Bar Screen -3 (Bottom motor)
14.9KW, 3PH, 415V
Condition: Motor submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
17 May 2026
COMPLETED AND DELIVERED
15
SCR-22 LL
Qty: 1 unit
Bar Screen -4 (Top motor)
0.55KW, 3PH, 415V
Condition: Motor submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
28 Apr 2026
COMPLETED AND DELIVERED
16
SCRV-22 LL
Qty: 1 unit
Bar Screen -4 (Bottom motor)
15HP, 3PH, 415V
Condition: Motor submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
17 May 2026
COMPLETED AND DELIVERED
17
GT-11 LL
Qty: 1 unit
Grit Chamber - 1
0.75KW, 3PH, 415V
Condition: Motor submerged in water
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
18 Apr 2026
COMPLETED AND DELIVERED
18
GP-11 LL
Qty: 1 unit
Grit Chamber - 1 pump room (Motor + Pump)
30KW, 3PH, 415V
Condition: Motor submerged in water. Pump impeller broken
Complete dismantling, Cleaning, Drying of stator winding, Replacenemt of DE...
03 May 2026
COMPLETED AND DELIVERED
Showing 16 to 30 of 60 units